China OEM Precision Die Casting 5G Telecom Radiator Housing - Reliable Suppliers from Factory
Process
Equipment & Material: 400T aluminum die casting machine; ADC12 material
- Material handle: 20±2mm, furnace temperature: 670°±20°;
- The use of secondary items is not allowed;
- Verify through testing that the material composition is suitable and can be manufactured;
- After die casting, first piece confirmation is required.
- Verify the filling quality of the surface. It’s not the bulge, it’s not the cold insulation, it’s not the lack of material in the pillars.
- Pay attention to the surface to prevent poor ejector pin crown, mold pulling or mold sticking.
- For non-machined surfaces and machined surfaces, the ejector pins are concave by 0-0.2 mm. The ejector pin must have a convex shape of 0-0.2 mm.
Equipment: A wooden stick / sawing machine
- Pay attention to the surface and don't damage it or use insufficient material.
- Adjust size and appearance.
Testing Instruments: Calipers, projection, three-dimensional modeling, visual appearance inspection
Check dimensions against drawings and use accurate measuring equipment.
Tools: Hydraulic presses, forming tools, and blade rulers
Warning: The accuracy of the front of the product is within 0.25 mm.
Tools & Equipment: Wind grinders, files, flat-bottom milling cutters, drill bits, tap processing fixtures, and 120# sandpaper
- Use CNC processing to process the through-hole of the tooth hole, the end face of the inner cavity, and the end face of the peripheral heat dissipation tooth face.
- Deburring: In order to make the product smooth in appearance, the sharp corners are chamfered and deburred, and the non-machined ejector pins are sharpened and polished.
- Complete check.
- Avoid over-cutting, leaving no sand holes, sharp edges, or missed processing; avoid scratches and burrs; and ensure smooth connection of the R corners.
- Control dimensional and shape tolerances to ensure that the processed surface finish reaches Ra 0.8.
- Regulation and non-regulation inspections.
- Verify product is flat relative to drawing.
- Handle items carefully to avoid deformation.
Remove surface particles, slag bags, gate residues, and product wire caps.
Make sure the mold closing line is connected smoothly and there is no leakage in processing. Also, avoid sharp corners and jagged edges.
Process: Two-color spraying at different locations uses a combination of powder spraying and oil spraying.
Test Instruments: Appearance visual inspection combined with colorimeter, film thickness meter, salt spray tester, hundred grid tester, alcohol resistance test, pencil test
- No contrasting colors, dirt, exposed bottoms, dust accumulation, scratches or other issues; tinted and anti-bake fractals are clearly visible;
- The color is completely consistent with the sample.
Standard quality inspection for incoming materials and in-process control post-outsourcing.
- Verify surface condition after powder coating;
- Holes must be randomly inspected using pin gauges, pass gauges, and stop gauges.
- 100% inspection of powder coated surfaces.
- Conduct irregular inspections for the purpose of powder coating performance testing.
- There is no obvious color, dirt, exposed bottom, dust accumulation, scratches, etc. in the coloring and baking-resistant fractal areas;
- The color exactly matches the sample.
Specification: Width and height are asymmetrically centered at 1.0±0.1, and glued to the designated strip area.
Tools: Dispensing jigs and machines
- The strips are even; they won't crack, pile up, pull, spill, deflect, blister, fall off, etc.
- Verify whether the glue cannot adhere or regenerate well, whether the glue strength is optimal, etc.
- SE4450 adhesive
- Five copper heat sinks
- Three metal plates
- Six half-round screws, M2.5*5
- The assembly position of the heat dissipation copper bar corresponding to the glue assembly;
- Fix the M2.5*5 screws of the sheet metal parts in the appropriate position and push the copper block to dissipate heat;
- Dispense glue into the copper row dispensing groove according to the sample;
- Make sure there are no loose or slipping teeth and that the locking screw is in a stable position.
Process: Carefully arrange items on the baking line into 2 columns and 7 rows, for a total of 14 items. Bake at 150°C for 30 minutes.
Equipment: Dryer
Leave enough space between products, be careful not to touch the tunnel door, hold lightly to avoid any bruises.
Final standard quality check before packaging phase.
- Appearance needs to be checked based on samples. There should be no dents, scratches or other blemishes on the surface and the glue application should be smooth and flawless!
- The tooth shape needs to match the pass gauge and stop gauge;
- Put the product into the knife card, cover the top of the knife card with a flat cardboard and package it.
Testing Instruments: Calipers, projectors, pin gauges, tooth gauges, visual and packaging inspection
If the measuring device is still within its calibration window.
Logistics alignment and documentation processing.
- Confirm that the quantity matches the order.
- Label and stamp the outer box.
- Send reports on shipments.
Inspection Instruments: Calipers, projectors, tooth gauges, needle gauges, appearance, outer packaging inspection
Whether the measuring device is still within its calibration window. Whether it meets both customer and SIP requirements.